Saltcoats Substation

Ayrshire

Back to Projects

This project involved the construction of a new 33 kV compound with switch room building and ducting & 132 kV structures and ducting.

  • Assembly and installation of Ballistic Screens in 33kV Compound
  • Construction of Switchgear Bases.
  • Construction of GT2A Cable Terminating Stanchions
  • Construction of Grid Cable Terminating Stanchions
  • Installation of Cable Ducts
  • Backfill & re-instate all 33kV feeder circuit joint bays & cable pulling pit to rear of switch room.
  • Repair of brick building and security wall defects
  • Demolition of existing 33kV Compound & Site Completion Works
  • Store ballistic Screens in 33kV from 132kV Compound
  • Backfill remaining joint bays & cable pulling pits.
  • Removal of decommissioned electrical apparatus by Robson’s demolition.
  • Demolition of existing 33kV and 132 KV concrete columns and bases.
  • Completion works to drainage, roadways & carpark in new 33kV switchgear enclosure area and 132kV live compound
  • Palisade fencing and gates to 132kV compound road and entrance and 33kV compound entrances.
  • Chippings to 132Kv and 33kV compounds
  • External works