This project involved the construction of a new 33 kV compound with switch room building and ducting & 132 kV structures and ducting.
- Assembly and installation of Ballistic Screens in 33kV Compound
- Construction of Switchgear Bases.
- Construction of GT2A Cable Terminating Stanchions
- Construction of Grid Cable Terminating Stanchions
- Installation of Cable Ducts
- Backfill & re-instate all 33kV feeder circuit joint bays & cable pulling pit to rear of switch room.
- Repair of brick building and security wall defects
- Demolition of existing 33kV Compound & Site Completion Works
- Store ballistic Screens in 33kV from 132kV Compound
- Backfill remaining joint bays & cable pulling pits.
- Removal of decommissioned electrical apparatus by Robson’s demolition.
- Demolition of existing 33kV and 132 KV concrete columns and bases.
- Completion works to drainage, roadways & carpark in new 33kV switchgear enclosure area and 132kV live compound
- Palisade fencing and gates to 132kV compound road and entrance and 33kV compound entrances.
- Chippings to 132Kv and 33kV compounds
- External works