Project:Altmouth Pumping Station

Client:Environment Agency


This Environment Agency contract involved

the construction of a new 33kv primary

substation with transformer plinth and bund

and included the replacement of the old diesel

run pumps with a new electric pumping system.


The scheme involved the following work elements:


 Reduced dig excavation

 Construction of 300mm reinforced concrete

    raft foundation and walls

 Reinforced concrete transformer plinth and    bund walls to water tight bunds at 33kv and    11kv

 Reinforced concrete slabs for associated    apparatus

 Power floated slab with service trenches and     cable pits

 Fabrication and installation of galvanised    support steelwork to 33kv cells

 Cavity wall construction

 Pre-cast concrete roof slabs

 Internal decoration

 Petrol interceptor and deep drainage

 Charcon P.C. troughs

 G.R.P. Doors

 Security fencing to transformer bund

 Top soiling and landscaping